Energy Project Updated 16 Oct 2006
The school board has awarded a contract to improve the energy efficiency of the district.  In addition to purchasing a $500,000 (est.) energy management system, the board is looking to move $1 million of projects from the building bond project to the energy project.

The board will not reduce the amount to be spent on the building project by $1 million if it is successful in transferring the items to the energy project (which does not require voter approval).  It is not clear what the board will do with the money that is freed up.

One thing is certain, any money the energy project frees from the building project becomes an increase in the cost of the building project, ceteris paribus.

The timeline for the Energy Project is as follows:
Execute Project Development Agreement September 22, 1999
Deliver CEA and Complete Draft Energy Performance Contract October 18, 1999
Execute Energy Performance Contract November 19, 1999

Back

Items in red were included in the building bond presented to the voters.

Facility

Work

Conceptual Estimate of Cost

High School

Replace AHUs and other ventilation upgrades

$     70,800

 

New roof

778,100

 

Renovate gym radiant heating system

29,300

 

Replace DW Valves

23,900

Middle School

Repair/Upgrade AHUs, AC coils

33,300

 

Improve ventilation, new AHU

31,900

 

Replace DW valves

23,900

Sacandaga

Repair windows

31,900

 

Upgrade AHUs

39,900

 

Replace DW valves

106,400

 

Boiler Repairs

14,600

Lincoln

Repair Windows

29,300

 

Replace 2 AHUs

26,600

 

Replace DW valves

10,600

Glen Worden

Renovate gym radiant heating system

29,300

 

Repair windows

28,600

 

Replace 3 AHUs

47,900

 

Replace DW valves

23,900

Glendaal

Improve cafeteria ventilation

23,900

 

Replace DW valves

10,600

 

Replace 3 AHUs

39,900

 

Repair windows

23,900

Bus Garage

Boiler replacement

30,600

 

Window replacement

13,300

District-wide

Energy management system

500,000

Total

$1,522,400

** A lighting retrofit program was completed within the past five years through the New York Power Authority. Opportunities for additional lighting system energy conservation may exist.  **

** This item is most annoying.  The board has already been told that the lighting system work it had done only 5 years ago was not the most efficient and the district could still save money by replacing the system again.